Regular service at 3 Circle Line stations to resume from April 6 with early completion of works

6 months ago 135

Updated

Apr 03, 2024, 01:00 PM

Published

Apr 03, 2024, 01:00 PM

SINGAPORE - Track work to integrate Stage 6 of the Circle Line (CCL) with the existing rail network has been completed more than a month ahead of schedule.

Regular service will resume between Kent Ridge and HarbourFront stations from April 6.

Since Jan 20, one platform each at the Telok Blangah and HarbourFront CCL stations were closed to facilitate the track work and a shuttle train operated on the other platform between HarbourFront and Labrador Park stations.

The measures were scheduled to be in place until May 24.

The Land Transport Authority (LTA) said on April 3 that it was possible to bring forward the resumption of service at the affected stations and reduce inconvenience to commuters because the track work was completed early.

This comes from additional resources deployed by the contractors to support the work to run round the clock, and refining work processes based on the site conditions, made in partnership with the contractors and SMRT, who operates the MRT line, according to LTA.

This final stage of the CCL will add three stops between HarbourFront and Marina Bay, closing the loop for the MRT line.

Transport Minister Chee Hong Tat thanked the engineers and workers for the effort and commuters for their patience during the work in his Facebook post on Wednesday, adding: “With this, the completion of the Circle Line is well under way, and we can look forward to the opening of the last three stations – Keppel, Cantonment, and Prince Edward – by 2026”.

...